How To Replace The RO Reverse Osmosis Membrane in Water Treatment System

Views: 0     Author: Site Editor     Publish Time: 2025-01-10      Origin: Site

Inquire

Part I: Preparation 

1.1 Prepare all tools that may be used during the construction process;

1.2 Clean the upstream water inlet pipeline;

1.3 Carefully evaluate the quality of the incoming water;

1.4 Check whether the pipeline has leaks;

1.5 Prepare water-soluble lubricant (chemically pure glycerin);

1.6 Ensure that all parts and chemicals used are complete;

1.7 Check the operation of the pre-treatment system and the normal water output.

IMG_8919


Part II: Dismantling of old reverse osmosis membrane and installation of new membrane

·  Dismantle the pressure vessel and store parts systematically.

·  Remove the old membrane and rinse the pressure vessel.

·  Check the brine seal ring on the new membrane for correct orientation.

·  Insert the new membrane element into the pressure vessel and apply lubricant to the "O" ring of the connecting pipe.

·  Repeat for additional membrane elements until all are installed.

·  Install the thrust ring and check the "O" ring on the element adapter.

·  Align and install the end plate clamping ring and adjust the gap with an adjustment sheet.

·  Repeat for all pressure vessels and connect external pipelines.

IMG_7793


Part III: Equipment Debugging 

1. Prepare for debugging: calibrate instruments, set sampling points, check connections, and test rotating equipment.

2. Open discharge valves and adjust the high-pressure pump outlet valve.

3. Use low-pressure pre-treated water to eliminate air from the system and check for leaks.

4. Perform low-pressure flushing for at least 6 hours or follow a soaking procedure.

5. Confirm all valves are correctly set and start the high-pressure pump with controlled flow.

6. Gradually open the high-pressure pump outlet valve and adjust recovery rates.

7. Check chemical dosages and measure inlet water pH.

8. After 1 hour of operation, record parameters and transition to automatic mode.

9. After 24-48 hours, review system performance data and confirm normal operation to complete construction.



 

 Email: info@navan-machine.com

 Phone: +86-19951353990
                 +86-512-58621580
 WhatsApp: +86-19951353990
 Address: HengLong Mansion, No 50 of RenMin MiddleRoad, Zhangjiagang City, Jiangsu, China

Product Category

Quick Links

Get In Touch

Copryright © 2023 BETA PLASTIC MACHINERY All Rights Reserved. Sitemap. Support by leadong.com. Privacy Policy.